Hounslow Council is behind on 80 per cent of the policies in its refreshed Net Zero 2030 plan, seven years after declaring a climate emergency, according to a report cited by MyLondon.
The council declared a climate emergency in 2019 and adopted a climate action emergency plan five years later. One year after the plan was refreshed, only 20 per cent of policies are on course to be delivered by 2030.
Among the biggest risks is the council’s plan to decarbonise its operational estate, including replacing gas boilers with heat pumps, fitting solar panels and adding energy efficiency measures.
Buildings and housing lag behind
Just one of the council’s 37 buildings has been decarbonised. A further 29 assets have been partially decarbonised, while seven have not been decarbonised at all.
The project is rated high risk because, in the council’s words, “the funding required to deliver decarbonisation of council operations to achieve net zero by 2030 is significant and not currently identified or available.”
Progress on council-managed social housing has also stalled. Hounslow had committed to decarbonising 16,000 homes by 2030, but only 150 have been fully decarbonised, with no further homes completed in 2026.
To meet its housing target, the council would need to carry out work on more than 5,200 homes a year. Council documents, however, indicate “limited further progress” is expected in 2027.
On schools, the council says it remains on track to decarbonise all schools by 2030, despite only one school being fully decarbonised in 2026.
The council’s vehicle fleet also remains heavily reliant on petrol and diesel. Of 492 vehicles, 359 are diesel or petrol powered, while 133 are hybrid or zero emission. Electric vehicles make up 2.2 per cent of the fleet, and no transitions were completed in 2026.
What the council plans next
Hounslow had also aimed to install 2,000 electric vehicle charging points by 2026, but missed that target. It has now halved the target and extended the deadline to 1,000 charging points by 2030.
The council says the earlier target was missed because of procurement delays and resourcing challenges. Feasibility studies found that about 1,000 lamp column charging points would be needed to meet its wider aim for residents without off-street parking.
Over the next 12 months, the council plans to complete decarbonisation projects at five leisure centres, Hanworth Air Park, Isleworth Public Hall and Cranford Library. It also plans to install HVO infrastructure at Bridge Road Depot and Spacewaye Civic Amenity site, and replace end-of-life internal combustion vehicles with ultra-low emission vehicles.