A major road in Croydon is set to close for four weeks while Network Rail replaces a 165-year-old railway bridge near Selhurst station.
Selhurst Road, part of the A213 between Croydon and Penge, will shut from 8am on Saturday, December 12 until 5pm on Sunday, January 10. The closure covers the section closest to the railway bridge.
Pedestrians will also be unable to use that stretch, and Edith Road will be closed to vehicles during the works. Network Rail said Selhurst station is due to stay open, but passengers have been warned to check before they travel because of the risk of sudden closures.
Why the road is closing
Network Rail said the bridge has already had multiple repairs and now needs to be fully replaced.
Lucy McAuliffe, Sussex route director for Network Rail, said: “We have carried out multiple repairs to the Selhurst Road railway bridge, but it has now reached the end of its serviceable life and needs to be replaced. We will assemble the new bridge on site and then move it into place between December 27 and January 2.”
The rail body said the closure needs to last longer than usual because utility pipes under the road mean engineers cannot use a heavy-lift crane. Instead, the new bridge will be assembled on site before being moved into place using self-propelled vehicles.
What residents and passengers should know
Network Rail said the bridge installation is scheduled to take place between December 27 and January 2.
The works have been timed to coincide with Christmas and New Year, when fewer people are expected to be driving or travelling by rail.
McAuliffe said: “We recognise the impact the works will have on residents, businesses, road users and our customers and apologise for the inconvenience caused. Wherever possible, we will minimise noise and disturbance and will provide advance notice of particularly disruptive activities.”
Read more via MyLondon.